Wednesday 21 December 2011

footings and the pad




merry christmas to us 


now have to wait a few weeks until the builders are off xmas break!!!!

Thursday 15 December 2011

ground work begins

10 dec 2011 

10 dec 2011

14th dec 2011

building licence

11 dec 2011

licence issued I picked up from council and hand delivered to Peter Stannard offices

time to get the pad down

development approval

11 nov 2011 application for development approved subject to conditions
1.  landscaping plan
2.  retic plan
3.  drainage fee paid before building licence issued
 so i draw up a quick plan of grass and kangaroo paws and a diagram of some pipes and valves went down to council with these and the drainage fee then waited

change of elevation

Can't have a skillion roof new elevation
just waiting for building licence
27 oct 2011

the changed plans



we have changed the plans and paid prelim fee 11th oct 2011

the builder


we found a design we could change quiet easy to suit our needs so we approached Peter Stannard and had them change the floor plans for the Mondo and have a skillion elevation

it begins

bought back in late september 2011